You have a shed, workshop or metal building that's freezing in winter. Your heater runs flat out and the room barely gets comfortable. If it's metal, you may also find water dripping off the inside of the roof on cold mornings.
Here's the short answer. Seal the gaps first. On metal, stop condensation at the sheet. Fit insulation between the studs and rafters. Put a vapour barrier on the warm side. Then line the walls. In a typical 3 × 2.4 m shed, that takes the heat you need from about 1.6 kW to about 0.3 kW. Materials cost roughly $20–40 per m² if you do it yourself. The steps below cover the order, the quantities and the mistakes that cause damp.
1. Measure the shed and set a budget
Measure every surface you'll insulate. Take this example shed: 3 m × 2.4 m, walls 2.1 m high, with a shallow pitched roof.
- Walls: 10.8 m perimeter × 2.1 m = 22.7 m², minus about 2.5 m² for the door and window = about 20 m²
- Roof: about 8 m²
- Floor: 7.2 m²
- Total: about 35 m²
Add 10% for offcuts. Check the stud and rafter depth too. Most sheds have 45–70 mm framing, and that sets your maximum insulation thickness.
| Item (per m²) | Typical DIY cost |
|---|---|
| Mineral wool, 75–100 mm | $5–10 |
| Rigid foam board (PIR), 50 mm | $10–20 |
| Vapour barrier film and tape | $1–2 |
| Plywood or OSB lining, 9–12 mm | $8–15 |
| Battens, fixings, foam, sealant | $2–4 |
Prices vary a lot by region and supplier. For 35 m², budget roughly $700–1,400. A professional fit costs more.
2. Fix leaks and damp before anything else
Insulation won't fix a wet shed. It makes one worse. Check the roof felt or sheets, the flashing and the base. Look for daylight through the roof and for staining on the timber.
Repair roof leaks. Make sure the floor sits off the ground on bearers, with an air gap underneath. Timber should feel dry. A cheap moisture meter helps: below about 20% moisture content is a sensible target before you close the walls in.
3. Seal the gaps
Air leaks can waste as much heat as the bare walls. The energy-saving guidance on air sealing and insulation treats sealing as the first job for good reason.
- Close the door, switch the light on outside at dusk, and look from inside for light at joints.
- Fill gaps under 6 mm with exterior-grade flexible sealant.
- Fill gaps of 6–25 mm with low-expansion foam.
- Fit brush or rubber draught strip around the door. Allow 1–2 hours.
- Seal around window frames and cable entries.
- On metal buildings, fit profiled foam filler strips where the roof sheets meet the walls and eaves.
Don't seal it completely shut. You'll add controlled ventilation in step 8.
4. Stop condensation on metal sheets
This step matters for metal sheds, steel buildings and pole barns. Warm, moist inside air hits the cold sheet, cools below its dew point, and drips. At 15 °C and 60% humidity, the dew point is about 7 °C. A steel sheet on a winter night is colder than that.
The fix is to stop moist air reaching the metal. Pick one method:
- Rigid foam bonded or fixed tight to the sheet. No air gap behind it. Tape every joint with foil tape.
- Closed-cell spray foam. It seals and insulates in one layer. On a large building or pole barn, hire a qualified installer. It needs proper protective equipment and ventilation.
- Anti-condensation membrane on new roof sheets. This only works when it's fitted to the sheet itself.
Never leave an unsealed, ventilated-from-inside gap between mineral wool and bare steel. That gap is where the water forms.
5. Fit the insulation
Wear gloves, goggles and a dust mask for mineral wool. Cut it with a long knife, about 10 mm oversize, so it friction-fits between studs.
Timber walls and roof
Fit a breathable membrane against the back of the cladding if there isn't one. Then fill the stud depth. With 70 mm studs, 75 mm mineral wool or 50 mm PIR fits well. Leave no gaps at the corners or top plates. A 5 mm gap around a foam board loses a noticeable share of its benefit, so foam the edges.
Metal walls and roof
Fix timber battens or studs to the frame first. Bond foam to the sheet as in step 4. Then you can add mineral wool between the battens for extra depth.
Floor
Lift the floorboards or work from below. Fit 50 mm foam between the joists. Alternatively, lay 25 mm foam over the existing floor with a new 18 mm board on top. This is quick but loses about 45 mm of height.
A shed of this size takes one person 2–3 days for steps 3–7.
6. Add the vapour barrier
The vapour barrier goes on the warm side of the insulation, facing into the room. It stops room moisture getting into the insulation.
- Use polythene vapour control film, about 0.125 mm (500 gauge).
- Overlap joints by 100–150 mm.
- Tape every overlap and every tear.
- Staple it to the studs every 300 mm.
Foil-faced PIR with foil-taped joints already counts as a vapour barrier. Don't add a second film over it with a cold gap in between.
7. Line the walls
Screw 9–12 mm plywood or OSB over the vapour barrier. Plywood takes shelf screws and survives knocks better than plasterboard in a workshop. Fix at 200–300 mm centres into the studs. Leave a 2–3 mm gap between sheets for movement.
Plan your wiring before you line. Any new sockets, lights or a circuit from the house should be designed and connected by a qualified electrician.
8. Ventilate and size the heater
Fit two small vents, one low and one high, about 100 cm² each. That keeps fresh air moving without undoing your sealing.
Now the running cost. The calculation uses heat loss in watts per degree (W/K). The temperature difference is 10 °C, keeping the shed at 15 °C on a 5 °C day. The example tariff is $0.25 per kWh. If you're in the UK, check current rates on the energy regulator's site and swap in your own figure.
- Before: 35 m² × U 4.0 = 140 W/K. Add a leaky door and window plus draughts, about 25 W/K. That gives 165 W/K × 10 °C = 1.65 kW.
- After: 35 m² × U 0.5 = 17.5 W/K. Add the door, window and reduced draughts, about 13 W/K. That gives about 30 W/K × 10 °C = 0.3 kW.
| Use: 6 h/day, 20 days/month | Before | After |
|---|---|---|
| Heat needed | 1.65 kW | 0.3 kW |
| kWh per day | 9.9 | 1.8 |
| Cost per day | $2.48 | $0.45 |
| Cost per month | $49.50 | $9.00 |
That's about $40 a month saved. Over a 5-month winter, that's roughly $200 a year. On a $700–1,400 job, payback is about 4–7 winters. Warm-up time adds a bit to both columns. You can learn how kWh and power ratings relate on the energy basics explainer.
Be honest about your use. If you heat the shed twice a month, payback stretches past 20 years. In that case, sealing gaps and a door strip, at under $50, is the only part that pays.
Keep any heater at least 1 m from shavings, fuel, paint and fabric. Never run fuel-burning heaters in a sealed shed. They produce moisture and dangerous fumes.
Common mistakes
- Putting mineral wool straight onto bare metal. Moist air reaches the cold sheet behind it. The wool soaks up condensation and stops working within one winter. Use bonded foam or spray foam against the metal.
- Fitting the vapour barrier on the wrong side, or fitting two. A barrier on the cold side traps moisture inside the wall. Two barriers trap it between them. Use one barrier, on the warm, room side.
- Insulating a shed that's still damp. If you close in wet timber or skip the roof repair, you seal the water in. Mould and rot follow. Dry it, fix it, then insulate.
Figures are worked examples: check your own tariff, the appliance labels and your local rules before you decide.
Watch or listen to this episode

I'm an Italian creator who builds apps, games and websites. I run GreenPlanet News with the help of AI tools: every article starts from the sources linked above, and I check what goes out. I'm not a doctor, a lawyer or a financial adviser. Spotted a mistake or have an idea? Write to me.
Instagram @spartaco_94_My websiteWrite to meAbout this blog



Green Investing 101: A Beginner's Guide to Sustainable Investments